Official TG-RERA record · not yet checked by our team

ASBL Lakeside

All ASBL projects on the TG-RERA record

By Ashoka Builders India Private Limited · Gachibowli, Ranga Reddy

Completion on file: 31 Mar 2022 · On-Going Project

What the filing tells a buyer

  • The completion date on file (31 Mar 2022) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 6,438 sq m (1.59 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
  • TG-RERA has issued an extension certificate for this project.
  • The builder reports 193 of 367 units booked (53%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02400001215
Builder (promoter)
Ashoka Builders India Private Limited
Project status
On-Going Project
Project type
Residential
Approving authority
HMDA
Completion date as first filed
31 Mar 2022
Litigation declared by builder
No
Units
367 (2 BHK, 3 BHK)
Towers or blocks
5
Floors (tallest block)
10 above ground, 2 basements
Total land
23,874 sq m (5.90 acres)
Land affected by road, lake FTL or nala widening
6,438 sq m (1.59 acres)
Approved built-up area
5,78,157 sq ft
Construction progress (builder reported)
100%
Survey numbers
Sy No. 449/P
Location
Puppalaguda Village, Gandipet Mandal, Gachibowli, Ranga Reddy, 500089

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error