Velpula Vanam

By Alwal Chakradhara & Velpula Raghavender · Rampally Dayara, Keesara, Medchal-Malkajgiri

Completion on file: 31 Dec 2019 · On-Going Project

What the filing tells a buyer

  • The completion date on file (31 Dec 2019) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 6,440 sq m (1.59 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02200000263
Builder (promoter)
Alwal Chakradhara & Velpula Raghavender
Project status
On-Going Project
Project type
Plotted Development
Approving authority
HMDA
Plan approval number
000058/LO/PLG/HMDA/2018
Completion date as first filed
31 Dec 2019
Litigation declared by builder
No
Total land
1,12,162 sq m (27.72 acres)
Land affected by road, lake FTL or nala widening
6,440 sq m (1.59 acres)
Approved built-up area
6,77,187 sq ft
Survey numbers
496P,497P,498P,586P,587P,500P
Location
Rampally Bogaram, Rampally Dayara, Keesara, Medchal-Malkajgiri, 501301

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps

Other registered projects nearby