Official TG-RERA record · not yet checked by our team
Vajram Aster Homes
By Vajram Constructions Pvt Ltd · Tellapur Road, Ranga Reddy
Completion on file: 30 Jul 2023 · On-Going Project
What the filing tells a buyer
- The completion date on file (30 Jul 2023) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
- 3,267 sq m (0.81 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
- The builder reports 33 of 78 units booked (42%). Builders update this figure themselves, so treat it as indicative.
Facts on the TG-RERA record
- TG-RERA registration
- REA02400000463
- Builder (promoter)
- Vajram Constructions Pvt Ltd
- Project status
- On-Going Project
- Project type
- Residential
- Approving authority
- GHMC
- Completion date as first filed
- 30 Jul 2023
- Litigation declared by builder
- No
- Units
- 78 (Villa)
- Towers or blocks
- 117
- Floors (tallest block)
- 3 above ground
- Total land
- 29,744 sq m (7.35 acres)
- Land affected by road, lake FTL or nala widening
- 3,267 sq m (0.81 acres)
- Approved built-up area
- 2,28,279 sq ft
- Construction progress (builder reported)
- 90%
- Location
- Gopanapally, Tellapur Road, Ranga Reddy, 500046
Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error