Official TG-RERA record · not yet checked by our team

The Square

By Ira Square Township Llp · Kongarakalan, Ibrahimpatnam, Ranga Reddy

Completion on file: 5 Apr 2028 · New Project

What the filing tells a buyer

  • The builder reports 48 of 131 units booked (37%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02400049682
Builder (promoter)
Ira Square Township Llp
Project status
New Project
Project type
Residential
Approving authority
HMDA
Plan approval number
12021/LO/Plg/HMDA/2021
Completion date as first filed
5 Apr 2028
Litigation declared by builder
No
Units
131 (4 BHK)
Towers or blocks
261
Floors (tallest block)
2 above ground
Total land
54,116 sq m (13.37 acres)
Land affected by road, lake FTL or nala widening
None declared
Approved built-up area
4,38,603 sq ft
Construction progress (builder reported)
10%
Survey numbers
60,61,383,384,385&386
Location
Kongarakalan, Ibrahimpatnam, Ranga Reddy, 501510

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error