Official TG-RERA record · not yet checked by our team

Suvela Projects

By Suvelaprojects · Khairatabad, KHAIRTABAD, Hyderabad

Completion on file: 14 Dec 2024 · New Project

What the filing tells a buyer

  • The completion date on file (14 Dec 2024) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 75 sq m (808 sq ft) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02500037907
Builder (promoter)
Suvelaprojects
Project status
New Project
Project type
Residential
Approving authority
GHMC
Plan approval number
1282/GHMC/KHB/2021-BP
Completion date as first filed
14 Dec 2024
Litigation declared by builder
No
Units
10 (3 BHK)
Towers or blocks
1
Floors (tallest block)
5 above ground, 1 basement
Total land
582 sq m (0.14 acres)
Land affected by road, lake FTL or nala widening
75 sq m (808 sq ft)
Approved built-up area
16,028 sq ft
Construction progress (builder reported)
11%
Survey numbers
94,95,96
Location
Anandnagar Colony, Khairatabad, KHAIRTABAD, Hyderabad, 500004

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps

Other registered projects nearby