Official TG-RERA record · not yet checked by our team

Sree Infras Altair

By Sree Infra Projects · Nallagandla Village, Serilingampally Mandal, Ranga Reddy District, Serilingampally, Ranga Reddy

Completion on file: 15 Jul 2025 · On-Going Project

What the filing tells a buyer

  • The completion date on file (15 Jul 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • The builder reports 6 of 10 units booked (60%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02400039164
Builder (promoter)
Sree Infra Projects
Project status
On-Going Project
Project type
Residential
Approving authority
GHMC
Plan approval number
2301/GHMC/SLP/2022-BP
Completion date as first filed
15 Jul 2025
Litigation declared by builder
No
Units
10
Towers or blocks
1
Floors (tallest block)
6 above ground
Total land
458 sq m (0.11 acres)
Land affected by road, lake FTL or nala widening
None declared
Approved built-up area
12,890 sq ft
Construction progress (builder reported)
79%
Survey numbers
SY NOs 302 TO 310, 320 AND 322, 324 AND 361, 363 TO 365, 384, 385, 387 TO 391 AND 399
Location
PLOT NO 11 IN CATEGORY HIG OF NALLAGANDLA RESIDENTIAL COMPLEX, SY NOs 302 TO 310, 320 AND 322, 324 AND 361, 363 TO 365, 384, 385, 387 TO 391 AND 399, Nallagandla Village, Serilingampally Mandal, Ranga Reddy District, Serilingampally, Ranga Reddy, 500019

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps

Other registered projects nearby