Official TG-RERA record · not yet checked by our team

Saket Pranamam

By Saket Engineers Pvt Ltd · Gowdavelly, Medchal-Malkajgiri

Completion on file: 12 Sept 2023 · On-Going Project

What the filing tells a buyer

  • The completion date on file (12 Sept 2023) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • The builder reports 75 of 90 units booked (83%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02200000137
Builder (promoter)
Saket Engineers Pvt Ltd
Project status
On-Going Project
Project type
Residential
Approving authority
HMDA
Plan approval number
000603/ZOC/R1/U6/HMDA/03032017
Completion date as first filed
12 Sept 2023
Litigation declared by builder
No
Units
90 (1 BHK, 2 BHK, 3 BHK, Studio, Studio 1)
Towers or blocks
1
Floors (tallest block)
5 above ground, 1 basement
Total land
22,935 sq m (5.67 acres)
Land affected by road, lake FTL or nala widening
None declared
Approved built-up area
1,28,120 sq ft
Construction progress (builder reported)
89%
Survey numbers
425(part)
Location
Ayodhya cross roads, Gowdavelly, Medchal-Malkajgiri, 501401

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps