Completion on file: 7 Oct 2025 · New Project
What the filing tells a buyer
- The completion date on file (7 Oct 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
- 987 sq m (0.24 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
Facts on the TG-RERA record
- TG-RERA registration
- REA00100072692
- Builder (promoter)
- An individual (name on the TG-RERA record)
- Project status
- New Project
- Project type
- Plotted Development
- Approving authority
- DTCP
- Completion date as first filed
- 7 Oct 2025
- Litigation declared by builder
- No
- Total land
- 25,403 sq m (6.28 acres)
- Land affected by road, lake FTL or nala widening
- 987 sq m (0.24 acres)
- Approved built-up area
- 1,58,718 sq ft
- Survey numbers
- 15/2/2/1,15/2/5 & 15/2/6
- Location
- Khanapur, Adilabad, Adilabad Urban, 504001
Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error