Official TG-RERA record · not yet checked by our team

Omsree Signet

By Om Sree Builders & Developers · Yapral Secunderabad, Alwal, Medchal-Malkajgiri

Completion on file: 1 May 2023 · New Project

What the filing tells a buyer

  • The completion date on file (1 May 2023) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 203 sq m (2,186 sq ft) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
  • The builder reports 304 of 319 units booked (95%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02200002162
Builder (promoter)
Om Sree Builders & Developers
Project status
New Project
Project type
Mixed Development (Residential & Commercial)
Approving authority
GHMC
Plan approval number
1/C28/06466/2019
Completion date as first filed
1 May 2023
Litigation declared by builder
No
Units
319
Towers or blocks
7
Floors (tallest block)
10 above ground
Total land
32,704 sq m (8.08 acres)
Land affected by road, lake FTL or nala widening
203 sq m (2,186 sq ft)
Approved built-up area
13,23,983 sq ft
Construction progress (builder reported)
82%
Survey numbers
202(P) & 203(P)
Location
Yapral Village, Yapral Secunderabad, Alwal, Medchal-Malkajgiri, 500087

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error