Completion on file: 11 Mar 2024 · New Project

What the filing tells a buyer

  • The completion date on file (11 Mar 2024) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 9,753 sq m (2.41 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02000072130
Builder (promoter)
An individual (name on the TG-RERA record)
Project status
New Project
Project type
Plotted Development
Approving authority
DTCP
Completion date as first filed
11 Mar 2024
Litigation declared by builder
No
Total land
22,055 sq m (5.45 acres)
Land affected by road, lake FTL or nala widening
9,753 sq m (2.41 acres)
Approved built-up area
2,37,404 sq ft
Survey numbers
48/P, 86&87/P
Location
Jangampalli, Yadagirigutta, Yadadri Bhuvanagiri, 503102

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error