Official TG-RERA record · not yet checked by our team

Lotus Aspira

By Lotus Infra Projects · Krushi Nagar,madinaguda, Serilingampally, Ranga Reddy

Completion on file: 30 Nov 2026 · New Project

What the filing tells a buyer

  • 1,542 sq m (0.38 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02400060509
Builder (promoter)
Lotus Infra Projects
Project status
New Project
Project type
Residential
Approving authority
GHMC
Completion date as first filed
30 Nov 2026
Litigation declared by builder
No
Units
83
Towers or blocks
1
Floors (tallest block)
7 above ground, 1 basement
Total land
4,197 sq m (1.04 acres)
Land affected by road, lake FTL or nala widening
1,542 sq m (0.38 acres)
Approved built-up area
1,09,176 sq ft
Construction progress (builder reported)
13%
Survey numbers
188
Location
Road No 13 ,, Krushi Nagar,madinaguda, Serilingampally, Ranga Reddy, 500049

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error