Official TG-RERA record · not yet checked by our team

Lakshmi Nilayam

By Rewaa Constructions · Plot No 549 & 550 in Sy No 565, PATANCHERU, Sangareddy

Completion on file: 18 Sept 2025 · New Project

What the filing tells a buyer

  • The completion date on file (18 Sept 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.

Facts on the TG-RERA record

TG-RERA registration
REA01100083849
Builder (promoter)
Rewaa Constructions
Project status
New Project
Project type
Residential
Approving authority
HMDA
Completion date as first filed
18 Sept 2025
Litigation declared by builder
No
Units
15
Towers or blocks
1
Floors (tallest block)
6 above ground, 1 basement
Total land
1,495 sq m (0.37 acres)
Land affected by road, lake FTL or nala widening
None declared
Approved built-up area
13,338 sq ft
Construction progress (builder reported)
0%
Survey numbers
565
Location
Plot No. 549 & 550 In Sy No. 565 of Muthangi Village, Plot No 549 & 550 in Sy No 565, PATANCHERU, Sangareddy, 502300

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps