Official TG-RERA record · not yet checked by our team
Individual
By Madu Satyanarayana · Amberpet, Hyderabad
Completion on file: 20 May 2025 · On-Going Project
What the filing tells a buyer
- The completion date on file (20 May 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
- 11,735 sq m (2.90 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
Facts on the TG-RERA record
- TG-RERA registration
- REA02500039216
- Builder (promoter)
- Madu Satyanarayana
- Project status
- On-Going Project
- Project type
- Plotted Development
- Approving authority
- HMDA
- Plan approval number
- 000088/L0/Plg/HMDA/2022
- Completion date as first filed
- 20 May 2025
- Litigation declared by builder
- No
- Total land
- 11,735 sq m (2.90 acres)
- Land affected by road, lake FTL or nala widening
- 11,735 sq m (2.90 acres)
- Approved built-up area
- 1,26,319 sq ft
- Location
- Bagh Amberpet, Amberpet, Hyderabad, 500013
Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error
Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps