Official TG-RERA record · not yet checked by our team

Four Square, Block-A

By Inspire Infra · Narsingi, Gandipet, Ranga Reddy

Completion on file: 11 Aug 2025 · On-Going Project

What the filing tells a buyer

  • The completion date on file (11 Aug 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 33 sq m (351 sq ft) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02400038932
Builder (promoter)
Inspire Infra
Project status
On-Going Project
Project type
Residential
Approving authority
DTCP
Plan approval number
0048/BP/3129/2022
Completion date as first filed
11 Aug 2025
Litigation declared by builder
No
Units
20
Towers or blocks
1
Floors (tallest block)
5 above ground
Total land
755 sq m (0.19 acres)
Land affected by road, lake FTL or nala widening
33 sq m (351 sq ft)
Approved built-up area
18,895 sq ft
Construction progress (builder reported)
10%
Survey numbers
340/2(OLD340/3)
Location
Narsingi, Gandipet, Ranga Reddy, 500075

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error

Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps

Other registered projects nearby