Official TG-RERA record · not yet checked by our team

Edla Laxmi Nilayam

By Pragnya Constructions · Arepally Road, Karimnagar urban, Karimnagar

Completion on file: 23 Aug 2025 · New Project

What the filing tells a buyer

  • The completion date on file (23 Aug 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • The builder reports 10 of 10 units booked (100%). Builders update this figure themselves, so treat it as indicative.

Facts on the TG-RERA record

TG-RERA registration
REA02700013173
Builder (promoter)
Pragnya Constructions
Project status
New Project
Project type
Residential
Approving authority
DTCP
Plan approval number
3011/W50/2019/4930
Completion date as first filed
23 Aug 2025
Litigation declared by builder
No
Units
10
Towers or blocks
1
Floors (tallest block)
6 above ground, 1 basement
Total land
532 sq m (0.13 acres)
Land affected by road, lake FTL or nala widening
None declared
Approved built-up area
13,371 sq ft
Construction progress (builder reported)
80%
Survey numbers
1355/1
Location
Arepally Road, Karimnagar urban, Karimnagar, 505001

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error