Official TG-RERA record · not yet checked by our team
Aavas Hyderabad
By Pacifica Construction Pvt Ltd · Bachupally, Medchal-Malkajgiri
Completion on file: 30 Jun 2025 · On-Going Project
What the filing tells a buyer
- The completion date on file (30 Jun 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
- 3,335 sq m (0.82 acres) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.
- TG-RERA has issued an extension certificate for this project.
- The builder reports 2,246 of 2,670 units booked (84%). Builders update this figure themselves, so treat it as indicative.
Facts on the TG-RERA record
- TG-RERA registration
- REA02200000148
- Builder (promoter)
- Pacifica Construction Pvt Ltd
- Project status
- On-Going Project
- Project type
- Residential
- Approving authority
- HMDA
- Plan approval number
- 000514/MED/R1/U6/HMDA/27012017
- Completion date as first filed
- 30 Jun 2025
- Litigation declared by builder
- No
- Units
- 2,670 (1 BHK, 2 BHK)
- Towers or blocks
- 7
- Floors (tallest block)
- 15 above ground
- Total land
- 38,285 sq m (9.46 acres)
- Land affected by road, lake FTL or nala widening
- 3,335 sq m (0.82 acres)
- Approved built-up area
- 16,63,159 sq ft
- Construction progress (builder reported)
- 88%
- Survey numbers
- 311(P),312(P),313(P),316(P),317(P)
- Location
- Miyapur - bollaram, Bachupally, Medchal-Malkajgiri, 500090
Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error
Site location as filed with TG-RERA. Map © OpenStreetMap contributors. Open in Google Maps