Official TG-RERA record · not yet checked by our team

7 Hills

By Kushal Sai Builders And Developers · Peerzadiguda, Medchal, Medchal-Malkajgiri

Completion on file: 10 Feb 2025 · New Project

What the filing tells a buyer

  • The completion date on file (10 Feb 2025) has passed and the project is not marked complete. Ask the builder for the current possession date in writing and check whether an extension has been granted.
  • 67 sq m (716 sq ft) of the land is marked as affected by road widening, a lake full tank level (FTL) or nala widening. The filing does not say which. Our full check confirms the lake buffer on the map.

Facts on the TG-RERA record

TG-RERA registration
REA02200038836
Builder (promoter)
Kushal Sai Builders And Developers
Project status
New Project
Project type
Residential
Approving authority
HMDA
Plan approval number
003960/BP/HMDA/0505/GHT/2021
Completion date as first filed
10 Feb 2025
Litigation declared by builder
No
Units
35 (2 BHK, 3 BHK)
Towers or blocks
1
Floors (tallest block)
6 above ground
Total land
1,625 sq m (0.40 acres)
Land affected by road, lake FTL or nala widening
67 sq m (716 sq ft)
Approved built-up area
41,966 sq ft
Construction progress (builder reported)
0%
Survey numbers
76/PART
Location
Medchal, Peerzadiguda, Medchal-Malkajgiri, 501401

Source: TG-RERA public project page, read on 4 Oct 2026. Figures are as filed by the builder. Report an error